Namib Minerals commissions expanded How Mine plant ahead of schedule

The plant, which was initially expected to reach full capacity by the end of December 2026 following a six-to-eight-week ramp-up after commissioning in mid-October, has already achieved its targeted processing rate.

Zimbabwe IndependentBy Valentine Tendai